Gruffalo
11-05-2010, 11:22 PM
Another cost cutting exercise in Infrastructure and another lame excuse from Dempsey to explain why:
A second high-profile rail project has fallen victim to the recession -- this time with a delay of at least six years.
The link-up between the Red and Green Luas lines in Dublin won't be finished before 2018 -- 13 years after it was first announced in the Government's Transport 21 programme.
The line was due to be finished in 2012 according to the original plans. The delay means the 5.6km line will also cost more than budgeted.
Internal documents on the project say construction is expected to begin in 2014, but this depends on planning permission being received by the end of this year. This is highly unlikely given that an application for a Railway Order has yet to be made.
The delay comes less than a week after Transport Minister Noel Dempsey was forced to admit he only became aware of a three-year delay to the €3bn DART Underground project from the media. A "breakdown in communications" meant Iarnrod Eireann, which is developing the line, did not inform the minister that the project was being pushed back from 2015 to 2018.
A spokesman for Mr Dempsey last night said the cross-city Luas line would not be built until a separate project -- Metro North -- was completed. This was because if construction works for both lines happened at the same time, it would bring the city to a standstill.
http://www.independent.ie/national-news/new-crosscity-line-to-link-luas-is-derailed-until-2018-at-earliest-2173955.html
It seems amazing how they have only discovered this problem now despite years of planning. It does seem like a good decision though as DART Underground will do most of what this line does, making this perhaps the most suitable line to be pushed back.
A second high-profile rail project has fallen victim to the recession -- this time with a delay of at least six years.
The link-up between the Red and Green Luas lines in Dublin won't be finished before 2018 -- 13 years after it was first announced in the Government's Transport 21 programme.
The line was due to be finished in 2012 according to the original plans. The delay means the 5.6km line will also cost more than budgeted.
Internal documents on the project say construction is expected to begin in 2014, but this depends on planning permission being received by the end of this year. This is highly unlikely given that an application for a Railway Order has yet to be made.
The delay comes less than a week after Transport Minister Noel Dempsey was forced to admit he only became aware of a three-year delay to the €3bn DART Underground project from the media. A "breakdown in communications" meant Iarnrod Eireann, which is developing the line, did not inform the minister that the project was being pushed back from 2015 to 2018.
A spokesman for Mr Dempsey last night said the cross-city Luas line would not be built until a separate project -- Metro North -- was completed. This was because if construction works for both lines happened at the same time, it would bring the city to a standstill.
http://www.independent.ie/national-news/new-crosscity-line-to-link-luas-is-derailed-until-2018-at-earliest-2173955.html
It seems amazing how they have only discovered this problem now despite years of planning. It does seem like a good decision though as DART Underground will do most of what this line does, making this perhaps the most suitable line to be pushed back.